Our Current Projects
1. Haggerston Castle Holiday Park, Berweek-on-Tweed
Building 132 Holiday Homes around 3 man-made Lakes for Bourne Leisure Ltd on a Haven Halidays Site
2. Western Distribution Road, Preston
1. Preston Western Distributor Road – Construction of 2 500m long road rail structures, 3 smaller structures over the highways and 2 culverts.
2. Separate from FRC works on PWDR, we have also undertaken Civils & Kerbing packages. This consisted of 48,000 meters of kerbs.
3. M1 Smart Motorways, Northampton
M1 Junct 13 - Junc 16 Smart Motorways Scheme
4. Curzone Street, Birmingham
Project Starting September 2022
5. Carol Green (HS2 Rail), Birmingham
Project Starting November 2022

4

5

1. Haggerston Castle Holiday Park, Berweek-on-Tweed
Barrett Civil Engineering secured it's first project for Bourne Leisure Ltd at Haggerston Castle Holiday Park in Berwick-on-Tweed, a Haven Holiday Site.
We are the main contractor on site, where we are carrying out all the aorks from cut & fill to final lanscaping with final delivery of 132 Holiday Home around 3 man-made lakes.
To date this is one of the largest extention to an already successful site that Bourne Leisure have taken.

2. Western Distribution Road, Preston
Project Details Coming Soon